The Problem
This company was experiencing problems with an aseptic area within their HVAC air flow. There were areas in the building where the airflow was not circulating properl.
How We Solved It
J.R.’s Maintenance started by completely remodeling the flow of the rooms in the building where air circulation was an issue. We set new sheet rock walls and then fabricated custom duct work from galvanized metal and custom returns from 316L stainless steel. Finally, we installed all of the custom-fit ductwork for the company’s HVAC system.
Customer Satisfaction
The customer now enjoys a fully functioning HVAC system. The remodel and the carefully placed custom ductwork increased the airflow in the low flow office area.